All Solved Qs Scrum Foundations Professional Certificate (SFPC) – (English)

PMI offers free project management courses during COVID-19 quarantines

Scrum Foundations Professional Certificate (SFPC) – (English) all questions solved. The sequence in the online test exam may vary for question on SFPC website but all questions are here.

We do not ensure a 100% result, but 70% just to keep the competition fair and easy.

PLEASE SEARCH QUESTION BELOW:

Scrum Foundations Professional Certificate (SFPC) – (English) SOLVED!!

  1. Which of the following are events in Scrum? CLICK FOR ANSWER
  2. Which of the following statements is TRUE about the definition of Done? CLICK FOR ANSWER
  3. __________ constitute the Spring Backlog and are often estimated in hours. Tasks
  4. The Scrum Master serves Product Owner in several ways, including: TRUE
  5. Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. TRUE
  6. During the sprint review the project is assessed against the ___________. CLICK FOR ANSWER
  7. Which of the following statements about a sprint are TRUE ____________ CLICK FOR ANSWER
  8. The ___________ control model requires that every piece of work is completely understood. Empirical Process
  9. Which Scrum meeting is focussed on getting feedback on the product from users and other stakeholders? Sprint Retrospective
  10. A line in Agile Manifesto reads “____________ over following a plan” Click for Answer
  11. _________ is responsible for the Scrum process? CLICK FOR ANSWER
  12. What is defined by the Scrum Framework? Rules & Roles + Artifacts and Events
  13. Scrum is based on the theory of constraints. FALSE
  14. Scrum Team is self-empowered to do whatever is necessary…? TRUE
  15. A ________ Chart is a graphical representation of work left to do versus time. Gantt
  16. The Scrum Team consists of a Product Owner, the Development Team and the Scrum Master. TRUE
  17. The Scrum Master is most like: Click for Answer
  18. When should estimation happen in Scrum? Sprint Planning
  19. Which topics should be discussed in the Sprint Review? CLICK FOR ANSWER
  20. The Scrum Teams are self-organizing and cross-functional? TRUE
  21. The daily Scrum is 30-minute time-boxed event: FALSE
  22. The term Agile Development was first introduced in: Click for Answer
  23. Scrum is not a process or a technique for building products. TRUE
  24. Scrum defines 3 roles, 5 events and 3 artifacts. TRUE
  25. What is the maximum time that Scrum recommends the team spends in daily scrum? CLICK FOR ANSWER
  26. Which meeting defines the start of a sprint? Sprint Planning
  27. Which of the following is not a Scrum Role? Agile Project Manager
  28. The heart of a Scrum is a Sprint? TRUE
  29. The Scrum Master serves the Product Owner in several ways: TRUE
  30. The Scrum Master is a servant-leader for the Scrum Team: TRUE
  31. Scrum users should frequently inspect artifacts and progress? TRUE
  32. At the end of the planning, the Development Team should not … FALSE
  33. Which of the following is the main purpose of the Daily Scrum: Click for Answer
  34. The ______________is responsible for delivering potentially shippable? Development Team
  35. Which of the following statements about the retrospective are true: Safety is important, in the meeting team discuss, the team should come up.
  36. Scrum is a collaborative effort involving developers and customers? FALSE
  37. Which system provides an evolutionary framework for incremental process improvement? Kaban
  38. What is the purpose of backlog refinement? To understand requirements
  39. Each new sprint starts immediately after the completion of the previous sprint. TRUE
  40. Which of the following are the artifacts in Scrum? Click for Answer